New electricity connection in Pakistan: ENC online apply, documents, security deposit per kW, demand notice, single or three phase and NEPRA's 30 day limit.

Most homes apply on the ENC portal at enc.com.pk, and NEPRA gives the company 30 days to connect a load of up to 15 kW. Pick your house size below to see the deposit, meter type and time limit.

Check your load, security deposit and connection time

Meter
Security deposit
Material cost
Deposit plus material
NEPRA time limit
`n
Usual market total, owner supplied, 13 Nov 2026
Rs 12,000 to Rs 25,000

Deposit rates come from Annexure IV of the NEPRA Consumer Service Manual and time limits from Annexure III. Material costs come from the Power Division: Rs 4,000 single phase or Rs 15,000 three phase up to 40 m, then Rs 200 or Rs 260 a metre up to 100 m. Loads above 15 kW and lines over 100 m need a site estimate. The demand notice your company issues is the amount you pay.

Apply online on enc.com.pk

PITC runs the Electricity New Connection system, known as ENC. Its menu covers the whole journey: Apply, Track, Print Form, Print DN, Pay DN and Upload DN. DN stands for demand notice.

Companies on the ENC portal

Company Where to apply
LESCO, GEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO, HAZECO enc.com.pk
IESCO iesco.enc.com.pk, the IESCO Smart App or a facilitation centre
FESCO fesco.enc.com.pk or the subdivision office
MEPCO MEPCO Smart App, Power Smart App, E-Ops or a facilitation centre
K-Electric K-Electric’s own new connection form

LESCO new connection

LESCO uses the main ENC portal for Lahore, Kasur, Okara, Sheikhupura and Nankana Sahib. In NEPRA’s latest review it was late on only 2.16% of eligible connections. LESCO’s own channel shows the online steps in this short video.

How to Apply for a New LESCO Meter from Home

Once your meter is in, the LESCO bill guide shows how to check the first bill.

MEPCO new connection

The ENC notice board sends MEPCO applicants to the MEPCO Smart App, the Power Smart App, E-Ops or a customer facilitation centre. MEPCO is also the slowest of the government companies. It left 6.33% of eligible applicants waiting past the deadline, above NEPRA’s 5% limit. Its MEPCO bill guide lists the facilitation routes.

IESCO and FESCO new connection

IESCO and FESCO have their own ENC sites. IESCO also takes requests through its apps and facilitation centres and was late on just 1.25%. FESCO’s FAQ says the form is free at the subdivision and installation takes about a month. It came close to the limit at 4.98%. The IESCO bill and FESCO bill guides cover each company.

GEPCO, PESCO, HESCO and TESCO

All four use the main portal. GEPCO also posts its new connection procedure on its website. PESCO and HESCO were late on 1.31% and 1.30%, and GEPCO on 3.08%. Our GEPCO bill, PESCO bill, HESCO bill and TESCO bill pages pick up from there.

K-Electric new connection

Karachi is not on ENC. K-Electric uses its own application form and process. It missed NEPRA’s limit too, with 5.84% of connections late.

ENC application steps

  1. 1

    Apply and print the form

    Choose Apply, enter your details and the load you need, then print the form. The application number is your tracking key.

  2. 2

    Site survey

    A company representative visits, checks the wiring test report and collects the paper documents at your premises.

  3. 3

    Demand notice

    The company prepares the cost estimate and issues the demand notice. Print it from Print DN.

  4. 4

    Pay and upload

    Pay at the bank or through Pay DN, then upload the paid copy with Upload DN.

  5. 5

    Work order and meter

    The company issues the service connection order, installs the line and fixes the meter.

Paying the demand notice

NEPRA’s manual gives you 30 days to pay the demand notice. On a written request, the company may allow another 30 days.

Track application status

Open enc.com.pk, choose Track and enter your application number. The status shows how far your file has moved. Keep the bank receipt too, in case the payment is not posted.

New connection documents

What the manual asks for

NEPRA’s Consumer Service Manual lists the papers to attach to the form.

Document Who needs it
Proof of ownership of the premises Every applicant
Affidavit on Rs 50 stamp paper: no earlier connection, any old dues will be paid, not a defaulter anywhere Every applicant
Attested CNIC copies of the applicant and a witness Every applicant
NOC from the owner, plus the owner’s ownership proof and affidavit Tenants
Attested CNIC copy of the landlord Tenants
Wiring test report Checked at the site survey

Forms on the ENC portal

The Downloads menu on ENC carries six files. They are the procedure, the conditions, the NOC, the affidavit and two undertakings, one against misuse of the connection and one against misuse of the tariff.

Old abadis without an approved map

The manual says no approved map, site plan or civic NOC is needed in old colonies and abadis where the land is inherited by native residents.

Security deposit and demand notice fee

The demand notice adds two things: a refundable security deposit and the cost of the line and meter.

Security deposit per kW

Connection Security deposit
Home, urban (A1) Rs 1,220 per kW
Home, rural (A1) Rs 610 per kW
Shop or office, urban (A2) Rs 1,810 per kW
Shop or office, rural (A2) Rs 920 per kW
Small industry (B1) Rs 1,580 per kW
Industry (B2) Rs 2,010 per kW
Agricultural tube well Rs 15,000 lump sum

A fraction of half a kW or more counts as a full kW, and less is ignored. The deposit is refunded when you apply for permanent disconnection with no dues outstanding.

Material cost and new meter fee

Connection Material up to 40 m 40 to 100 m Material for 80 m Deposit, urban Deposit, rural
Single phase, 3 kW Rs 4,000 Rs 200 per m Rs 12,000 Rs 3,660 Rs 1,830
Three phase, 5 kW Rs 15,000 Rs 260 per m Rs 25,400 Rs 6,100 Rs 3,050

These examples come from the Power Division’s billing guide. A house more than 100 m from the pole, or a load above 15 kW that needs a transformer, gets a site estimate instead.

Demand notice for a house 80 m from the pole, urbanRs

Our sum of the Power Division's material costs and NEPRA's security deposit rates. Your demand notice may differ.

What people pay in the market

The official figures above are the floor. The site owner checked what homes actually pay on 13 November 2026.

Item Owner supplied market figure, 13 November 2026
Demand notice Usually Rs 6,000 to Rs 8,000
Meter About Rs 20,000 if you buy it yourself
Wire from the pole to the meter Provided by the company
Total for a new connection Usually Rs 12,000 to Rs 25,000

The total depends on the wire length, getting the file completed and other local factors. For some months the companies asked consumers to buy their own meter. They now supply the meter again, so check before you buy one. Costs vary by company and area, and these are not official NEPRA or company rates.

Other fees in the manual

Request Single phase Three phase
Shifting the meter Rs 500 plus extra material Rs 1,000 plus extra material
Meter accuracy check on your request Rs 500 Rs 1,000

Single phase vs three phase

Load by house size

NEPRA’s manual uses these planning loads for houses. Your own sanctioned load depends on what you list on the form.

House Planning load
3 marla 3.15 kW
5 marla 5.0 kW
7 marla 5.70 kW
10 marla 6.60 kW
12 marla 7.45 kW
14 marla 8.75 kW
1 kanal 10.61 kW
2 kanal 17.74 kW

When a ToU meter applies

Under S.R.O. 279(I)/2026, a home with a sanctioned load of 5 kW or more is billed on a time of use meter, with separate peak and off peak rates. The Power Division’s own examples use single phase for 3 kW and three phase for 5 kW.

Planning for solar later

NEPRA’s 2026 net billing rules are written for three phase connections, and a solar system cannot be larger than your sanctioned load. If rooftop solar is likely, ask for three phase and enough load now. Our net metering guide explains the rest.

Changing the load later

A load increase uses the same application form as a new connection, and the deposit is recalculated for the whole load at current rates. A load reduction refunds or charges only the difference.

How long a new connection takes

NEPRA time limits by load

Category Load Sanctioned by Time limit
1 Up to 15 kW at 400 V SDO for homes, shops and general services 30 days
2 Above 15 kW to 70 kW XEN 44 days
3 Above 70 kW to 500 kW SE 58 days
4 Above 500 kW to 5,000 kW at 11 or 33 kV CEO 106 days

The 30 days for a home

Category 1 connection, up to 15 kW
  1. 4 daysRegistration and survey

    Application registered, wiring test report checked and the site surveyed.

  2. 6 daysEstimate and demand notice

    Cost estimate prepared and checked, demand notice issued.

  3. 11 daysWork order and material

    Service connection order issued, material drawn from the store and the line built.

  4. 9 daysMeter installed

    The meter is fixed and the connection energised.

Companies that miss the deadline

Share of new connections given late, 2024 to 2025%

NEPRA Performance Evaluation Report, distribution companies, FY 2024 to 2025. Limit: 5% late.

QESCO and SEPCO also apply through the main ENC portal. Our QESCO bill and SEPCO bill guides list each company’s documents and charges.

When your connection is late

Complain first at the subdivision or the company’s complaint cell, quoting your application number and payment date. NEPRA’s manual says connections must follow its time schedule. If the company does not act, take the case to NEPRA through its Asaan Approach app.

Sources and last check

Official documents

Documents, deposits, time limits, house loads, sanctioning officers and other fees come from NEPRA’s Consumer Service Manual of January 2021, Annexures I, III, IV and VI. Material costs come from the Power Division’s billing guide. Late connection figures come from NEPRA’s Performance Evaluation Report for FY 2024 to 2025. The ToU rule comes from S.R.O. 279(I)/2026.

Portals and reports

Company routes come from the ENC portal notice board and the GEPCO, TESCO and FESCO websites. The deposit petitions and NEPRA’s hearing were reported in January and February 2025. Market costs are owner supplied market figures from 13 November 2026. All were checked on 13 November 2026.

Frequently asked questions

How much is the fee for a new single phase meter?

The Power Division lists Rs 4,000 for material up to 40 metres on a 3 kW single phase connection. The security deposit adds Rs 3,660 in a city or Rs 1,830 in a village. Your demand notice shows the exact amount for your address.

How many days does a new electricity connection take?

NEPRA's Consumer Service Manual gives the company 30 days for a load of up to 15 kW. It allows 44 days up to 70 kW and 58 days up to 500 kW. The steps are registration and survey, the demand notice, the work order and meter installation.

How can I track my new connection application?

Open enc.com.pk, choose Track and enter the application number from your form. The same menu lets you print the form, print the demand notice, pay it and upload the paid copy, so keep that number safe.

What documents are needed for a new electricity connection?

You need proof of ownership, a Rs 50 affidavit that no earlier connection or unpaid dues exist, attested CNIC copies of you and a witness, and a wiring test report. Tenants also need the owner's NOC and affidavit.

Should I take a single phase or three phase connection?

The Power Division's examples use single phase for a 3 kW load and three phase for 5 kW. At 5 kW and above the home tariff moves to a time of use meter, and solar net billing is written for three phase connections, so plan ahead.