Most homes apply on the ENC portal at enc.com.pk, and NEPRA gives the company 30 days to connect a load of up to 15 kW. Pick your house size below to see the deposit, meter type and time limit.
Apply online on enc.com.pk
PITC runs the Electricity New Connection system, known as ENC. Its menu covers the whole journey: Apply, Track, Print Form, Print DN, Pay DN and Upload DN. DN stands for demand notice.
Companies on the ENC portal
| Company | Where to apply |
|---|---|
| LESCO, GEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO, HAZECO | enc.com.pk |
| IESCO | iesco.enc.com.pk, the IESCO Smart App or a facilitation centre |
| FESCO | fesco.enc.com.pk or the subdivision office |
| MEPCO | MEPCO Smart App, Power Smart App, E-Ops or a facilitation centre |
| K-Electric | K-Electric’s own new connection form |
LESCO new connection
LESCO uses the main ENC portal for Lahore, Kasur, Okara, Sheikhupura and Nankana Sahib. In NEPRA’s latest review it was late on only 2.16% of eligible connections. LESCO’s own channel shows the online steps in this short video.

Once your meter is in, the LESCO bill guide shows how to check the first bill.
MEPCO new connection
The ENC notice board sends MEPCO applicants to the MEPCO Smart App, the Power Smart App, E-Ops or a customer facilitation centre. MEPCO is also the slowest of the government companies. It left 6.33% of eligible applicants waiting past the deadline, above NEPRA’s 5% limit. Its MEPCO bill guide lists the facilitation routes.
IESCO and FESCO new connection
IESCO and FESCO have their own ENC sites. IESCO also takes requests through its apps and facilitation centres and was late on just 1.25%. FESCO’s FAQ says the form is free at the subdivision and installation takes about a month. It came close to the limit at 4.98%. The IESCO bill and FESCO bill guides cover each company.
GEPCO, PESCO, HESCO and TESCO
All four use the main portal. GEPCO also posts its new connection procedure on its website. PESCO and HESCO were late on 1.31% and 1.30%, and GEPCO on 3.08%. Our GEPCO bill, PESCO bill, HESCO bill and TESCO bill pages pick up from there.
K-Electric new connection
Karachi is not on ENC. K-Electric uses its own application form and process. It missed NEPRA’s limit too, with 5.84% of connections late.
ENC application steps
- 1
Apply and print the form
Choose Apply, enter your details and the load you need, then print the form. The application number is your tracking key.
- 2
Site survey
A company representative visits, checks the wiring test report and collects the paper documents at your premises.
- 3
Demand notice
The company prepares the cost estimate and issues the demand notice. Print it from Print DN.
- 4
Pay and upload
Pay at the bank or through Pay DN, then upload the paid copy with Upload DN.
- 5
Work order and meter
The company issues the service connection order, installs the line and fixes the meter.
Paying the demand notice
NEPRA’s manual gives you 30 days to pay the demand notice. On a written request, the company may allow another 30 days.
Track application status
Open enc.com.pk, choose Track and enter your application number. The status shows how far your file has moved. Keep the bank receipt too, in case the payment is not posted.
New connection documents
What the manual asks for
NEPRA’s Consumer Service Manual lists the papers to attach to the form.
| Document | Who needs it |
|---|---|
| Proof of ownership of the premises | Every applicant |
| Affidavit on Rs 50 stamp paper: no earlier connection, any old dues will be paid, not a defaulter anywhere | Every applicant |
| Attested CNIC copies of the applicant and a witness | Every applicant |
| NOC from the owner, plus the owner’s ownership proof and affidavit | Tenants |
| Attested CNIC copy of the landlord | Tenants |
| Wiring test report | Checked at the site survey |
Forms on the ENC portal
The Downloads menu on ENC carries six files. They are the procedure, the conditions, the NOC, the affidavit and two undertakings, one against misuse of the connection and one against misuse of the tariff.
Old abadis without an approved map
The manual says no approved map, site plan or civic NOC is needed in old colonies and abadis where the land is inherited by native residents.
Security deposit and demand notice fee
The demand notice adds two things: a refundable security deposit and the cost of the line and meter.
Security deposit per kW
| Connection | Security deposit |
|---|---|
| Home, urban (A1) | Rs 1,220 per kW |
| Home, rural (A1) | Rs 610 per kW |
| Shop or office, urban (A2) | Rs 1,810 per kW |
| Shop or office, rural (A2) | Rs 920 per kW |
| Small industry (B1) | Rs 1,580 per kW |
| Industry (B2) | Rs 2,010 per kW |
| Agricultural tube well | Rs 15,000 lump sum |
A fraction of half a kW or more counts as a full kW, and less is ignored. The deposit is refunded when you apply for permanent disconnection with no dues outstanding.
Material cost and new meter fee
| Connection | Material up to 40 m | 40 to 100 m | Material for 80 m | Deposit, urban | Deposit, rural |
|---|---|---|---|---|---|
| Single phase, 3 kW | Rs 4,000 | Rs 200 per m | Rs 12,000 | Rs 3,660 | Rs 1,830 |
| Three phase, 5 kW | Rs 15,000 | Rs 260 per m | Rs 25,400 | Rs 6,100 | Rs 3,050 |
These examples come from the Power Division’s billing guide. A house more than 100 m from the pole, or a load above 15 kW that needs a transformer, gets a site estimate instead.
Our sum of the Power Division's material costs and NEPRA's security deposit rates. Your demand notice may differ.
What people pay in the market
The official figures above are the floor. The site owner checked what homes actually pay on 13 November 2026.
| Item | Owner supplied market figure, 13 November 2026 |
|---|---|
| Demand notice | Usually Rs 6,000 to Rs 8,000 |
| Meter | About Rs 20,000 if you buy it yourself |
| Wire from the pole to the meter | Provided by the company |
| Total for a new connection | Usually Rs 12,000 to Rs 25,000 |
The total depends on the wire length, getting the file completed and other local factors. For some months the companies asked consumers to buy their own meter. They now supply the meter again, so check before you buy one. Costs vary by company and area, and these are not official NEPRA or company rates.
Other fees in the manual
| Request | Single phase | Three phase |
|---|---|---|
| Shifting the meter | Rs 500 plus extra material | Rs 1,000 plus extra material |
| Meter accuracy check on your request | Rs 500 | Rs 1,000 |
Single phase vs three phase
Load by house size
NEPRA’s manual uses these planning loads for houses. Your own sanctioned load depends on what you list on the form.
| House | Planning load |
|---|---|
| 3 marla | 3.15 kW |
| 5 marla | 5.0 kW |
| 7 marla | 5.70 kW |
| 10 marla | 6.60 kW |
| 12 marla | 7.45 kW |
| 14 marla | 8.75 kW |
| 1 kanal | 10.61 kW |
| 2 kanal | 17.74 kW |
When a ToU meter applies
Under S.R.O. 279(I)/2026, a home with a sanctioned load of 5 kW or more is billed on a time of use meter, with separate peak and off peak rates. The Power Division’s own examples use single phase for 3 kW and three phase for 5 kW.
Planning for solar later
NEPRA’s 2026 net billing rules are written for three phase connections, and a solar system cannot be larger than your sanctioned load. If rooftop solar is likely, ask for three phase and enough load now. Our net metering guide explains the rest.
Changing the load later
A load increase uses the same application form as a new connection, and the deposit is recalculated for the whole load at current rates. A load reduction refunds or charges only the difference.
How long a new connection takes
NEPRA time limits by load
| Category | Load | Sanctioned by | Time limit |
|---|---|---|---|
| 1 | Up to 15 kW at 400 V | SDO for homes, shops and general services | 30 days |
| 2 | Above 15 kW to 70 kW | XEN | 44 days |
| 3 | Above 70 kW to 500 kW | SE | 58 days |
| 4 | Above 500 kW to 5,000 kW at 11 or 33 kV | CEO | 106 days |
The 30 days for a home
- 4 daysRegistration and survey
Application registered, wiring test report checked and the site surveyed.
- 6 daysEstimate and demand notice
Cost estimate prepared and checked, demand notice issued.
- 11 daysWork order and material
Service connection order issued, material drawn from the store and the line built.
- 9 daysMeter installed
The meter is fixed and the connection energised.
Companies that miss the deadline
NEPRA Performance Evaluation Report, distribution companies, FY 2024 to 2025. Limit: 5% late.
QESCO and SEPCO also apply through the main ENC portal. Our QESCO bill and SEPCO bill guides list each company’s documents and charges.
When your connection is late
Complain first at the subdivision or the company’s complaint cell, quoting your application number and payment date. NEPRA’s manual says connections must follow its time schedule. If the company does not act, take the case to NEPRA through its Asaan Approach app.
Sources and last check
Official documents
Documents, deposits, time limits, house loads, sanctioning officers and other fees come from NEPRA’s Consumer Service Manual of January 2021, Annexures I, III, IV and VI. Material costs come from the Power Division’s billing guide. Late connection figures come from NEPRA’s Performance Evaluation Report for FY 2024 to 2025. The ToU rule comes from S.R.O. 279(I)/2026.
Portals and reports
Company routes come from the ENC portal notice board and the GEPCO, TESCO and FESCO websites. The deposit petitions and NEPRA’s hearing were reported in January and February 2025. Market costs are owner supplied market figures from 13 November 2026. All were checked on 13 November 2026.

Frequently asked questions
How much is the fee for a new single phase meter?
The Power Division lists Rs 4,000 for material up to 40 metres on a 3 kW single phase connection. The security deposit adds Rs 3,660 in a city or Rs 1,830 in a village. Your demand notice shows the exact amount for your address.
How many days does a new electricity connection take?
NEPRA's Consumer Service Manual gives the company 30 days for a load of up to 15 kW. It allows 44 days up to 70 kW and 58 days up to 500 kW. The steps are registration and survey, the demand notice, the work order and meter installation.
How can I track my new connection application?
Open enc.com.pk, choose Track and enter the application number from your form. The same menu lets you print the form, print the demand notice, pay it and upload the paid copy, so keep that number safe.
What documents are needed for a new electricity connection?
You need proof of ownership, a Rs 50 affidavit that no earlier connection or unpaid dues exist, attested CNIC copies of you and a witness, and a wiring test report. Tenants also need the owner's NOC and affidavit.
Should I take a single phase or three phase connection?
The Power Division's examples use single phase for a 3 kW load and three phase for 5 kW. At 5 kW and above the home tariff moves to a time of use meter, and solar net billing is written for three phase connections, so plan ahead.